What Are the Advantages of EPC Mining Pipeline Solutions?

10 Mar.,2025

 

EPC Projects Deliver Flexibility Needed by Mining Industry

In the mining industry, coping with uncertainty is part of the business. Whether extracting metals or industrial minerals, it is typical for mining operations to encounter obstacles or conditions that may not have been fully anticipated, even in the most detailed plans.

View Details

That's why project delivery for design and construction of critical mining infrastructure must be flexible and adaptable. Whether it involves electrical distribution systems, water and wastewater treatment, on-site power generation, material handling, maintenance and administrative facilities, or other systems needed for mining operations, the project delivery model must account for the uncertainties of schedule, budget and unknown obstacles.

Consider EPC Delivery

There may be some misconceptions about whether an engineer-procure-construct (EPC) project delivery framework allows the necessary flexibility to adjust to unexpected mining project demands while meeting aggressive schedules for completion.

The overall flexibility afforded by an EPC process ' even after construction is underway ' can be the solution owners need. Also called progressive EPC or integrated EPC, these contract frameworks have something in common: integrating all stakeholders from owners and regulators to permitting, procurement, engineering and construction teams in upfront, open-book reviews that can facilitate critical communication needed for adjustments.

Procurement Made Easier

Under this EPC model, specifications for items with long lead times ' everything from high-dollar electrical transformers, breakers and switches to conveyors, pumps, motors and pipe ' can be developed while engineering design is in a relatively early stage. With procurement on the owner's paper, needed flexibility can be achieved, even if project scope evolves beyond original plans.

Whether the equipment and materials are needed for specific operations or for more general balance-of-plant applications, the open-book process can optimize the planning and design because it gives owners insight and direct input on decisions that are critical to setting the overall direction of the project. Periodic reviews enable all stakeholders to track the cost impacts of all scope modifications. Those insights lead to more informed cost-benefit decisions, such as whether adding specific elements to the project really is necessary.

An additional benefit of this integrated EPC approach is the identification of equipment or materials that can be fabricated in controlled off-site shop environments and then delivered just in time for field installation. This accelerated engineering design reduces overall project costs but requires the owner, engineer and construction team to work together early in the project to meet schedule demands.

Transferring Risk

Under a conventional design-bid-build contract, the engineer is typically responsible for developing project cost estimates based on scopes of the various phases. However, the engineer may not be able to anticipate many of the risks that regularly come with the territory once construction begins. Without an accurate project scope, estimates are likely to be inaccurate, leaving the burden on the backs of the owner and construction team to resolve any discrepancies.

The partnership approach fostered under EPC project delivery can help an owner understand that spending a little more on engineering design can result in big savings during procurement and construction, where 90% ' or more ' of costs are typically incurred. This partnership approach can also allow the project team to be nimbler when changes to the project scope are required, resulting in a better experience for all stakeholders.

Success hinges on getting more construction input at earlier stages of design and project development. This can only happen with close collaboration that emphasizes transparent and open communication. Only fully integrated EPC firms can execute in this manner.

Brownfield and Greenfield

It is common to assume that an EPC framework is best suited for a greenfield project built from the ground up; however, the EPC model works equally well for both new construction on greenfield sites and for brownfield retrofits on existing facilities. In fact, advanced technologies like laser scanning can be a big boost in developing 3D models for brownfield retrofits within existing facilities. With upfront collaboration and open-book transparency, the process efficiencies apply for either type of project. Burns & McDonnell has a long history of executing retrofit projects with this approach.

Are There Other Risks With EPC?

You will get efficient and thoughtful service from Dragon.

No project ever proceeds exactly as planned, whether in mining or any other industry, and there is no one-size-fits-all contract framework that works equally well for every project. But no matter the flavor of the contract, any method that promotes an atmosphere of partnership and trust will be key to creating the flexibility needed to pivot and adjust.

Intense collaboration does take more effort. But defining scope with all the details subject to discussion can lead to understanding and then agreement on fair compensation reflecting the risk the owner and contractor are sharing.

A partnership approach typically results in a project with deliverables that all are happy with, and this can be the foundation for a win-win relationship.

Project implementation methods in successful mining and metals ...

Industrial plant projects are often investments of tens or even hundreds of millions of euros. Getting the investment to produce within the planned time frame is naturally the owner's primary interest. Therefore, the engineering company needs not only the technical expertise, but also the ability to meet customer goals in a flexible and timely manner.
Open and service-oriented EPCM ' typical solution for Mining and Metals project implementation

EPCM (engineering, procurement, construction management) is a commonly used investment project implementation model where the EPCM supplier, i.e. the engineering contractor, does all the technical design necessary for the investment and co-ordinates the implementation with the owner. The owner's role is to make decisions. In EPCM model engineering contractor is responsible for technical design, procurement and site control, and also supports the owner in making right-time decisions on technical solutions, equipment and equipment suppliers, building materials and contractors, and other investment-related choices throughout the project.

A good engineering contractor is an engineering company that is independent from technology suppliers, is familiar with the latest technologies in the field, and able to help the owner in choosing the most suitable solution for any specific item. An independent engineering contractor compares and combines the best unit processes of different suppliers and can utilize the latest intelligent process models in objects and incorporate them into the owner's control systems.

From the owner's perspective, it is important that the project management processes and information flow are transparent and the implementation highly service-oriented. Owner's interests are guiding decision making and corrective actions are taken immediately. The owner must be able to follow the project's progress, costs, and technology choices throughout the investment life cycle. A smooth project management and the best outcome are always in the interests of both the owner and the engineering contractor.

The EPCM model is clearly more risk-free than many other implementation models, and as a whole, a less expensive option. It is also a flexible and 'open' implementation method as the owner has full visibility to the costs and progress. Decisions and contracts are made as the project progresses, making it easier to select the best techno-economical solution for each situation at the right time. It is also a very flexible model. While the key guidelines for the investment project are already being decided in the project's development phase, in practice, refinements, changes and unexpected situations are always met during the project. When the owner is not legally tied into one EPC agreement, the agility is kept and the investor can always make appropriate changes / decisions during the process.

In EPCM implementation model, the organization is piled up specifically for the project, and the project is resourced with the best experts. It is important to remember that people are who make project a success, regardless of the way it is implemented, and that when the EPCM implementation ends, the EPCM contractor's project staff will no longer incur any cost to the owner.

EPC model ' the delivery solution locked at an early stage

Alternatively, the owner may want to purchase a larger entity. Another commonly used implementation model is EPC (engineering, procurement, construction), which means more or less a turnkey delivery. For example, the EPC model can be utilised when the investor has little or no willingness to participate in the project due to the lack of own resources. In this case, a total delivery solution is agreed, in which the process equipment supplier typically handles the entire project to execute the finished package according to the specifications agreed at an early stage.

The challenge with the EPC model is that the overall delivery scope is locked at the time of signing the contract. When an EPC contract is made, the technical information of the investment is often still inadequate and the supply content is then difficult to influence. Thus, changes to the contract and delivery content are always expensive for the owner. A good EPC agreement takes the owner's interests into account but requires a high-level professionalism. It also takes a long time to prepare such a contract. If the EPC delivery includes elements outside the supplier's core competence, the total investment price may increase as the EPC contractor always adds its' own profit margins and risk allowances to the supply. EPC contractor can also select the sub-suppliers based on the lowest costs, in order to maximize own profit. The owner does not have visibility of the cost composition and thus any savings will benefit only the EPC contractor.

Construction is often the largest single cost element in industrial investments. Due to the EPC contractor's profit margins and risk reservations, the EPC model often costs more than the EPCM implementation. The same applies to process control and electrification. It is also essential to remember that risk reservations are included in the price of the EPC contract, even if none or only a part of the project risks are realized.

In the EPC model, the customer is tied to one delivery contract and supplier, and is no longer able to influence the design or implementation.

EPC delivery can be included in an EPCM project

In the EPCM implementation model, certain process equipment or equipment deliveries can be obtained with an EPC model, i.e. turnkey delivery, including process guarantees. In this way, the process risks of the actions can be managed easily, but the possibility for the project owner to make agile changes is maintained.

An EPCM implementation method can still include larger scopes from key suppliers, enabling the owner to benefit from the suppliers' standardization, and simultaneously providing the suppliers a chance to direct all their energy and power into their respective core business.

Is EPCM model suitable only for major projects?

EPCM implementation is also widely used for small investment and maintenance projects. The fundamental logic is the same as in larger projects, only the scale is smaller. Small investments are often made without the important project development phases, which may then lead the project into unpleasant surprises. In the EPCM implementation these surprises are more manageable and, above all, more cost-effective to manage because the EPCM offers flexibility and agility to make changes even after the implementation decision.

If you want to learn more, please visit our website EPC Mining Pipeline Solutions.